Paerdegat Athletic Center Boiler Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the boiler at the Paerdegat Athletic Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2020
Projected Completion Date: February 2021
Completion Date: March 2021

Procurement

Start Date: March 2021
Projected Completion Date: November 2021
Completion Date: March 2022

Construction

Start Date: May 2022
Projected Completion Date: May 2023
Completion Date: February 2023

Understand how we build parks.

Funding

Total Funding: $500,000
Funding Source: Mayoral

Location

Paerdegat Basin Park, Brooklyn
1500 Paerdegat Avenue North
Community Board: 18

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024