Linden Park Multipurpose Play Area Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the multipurpose play area at Linden Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2020
Projected Completion Date:
October 2021
Completion Date:
November 2021
Procurement
Start Date: November 2021
Projected Completion Date:
August 2022
Adjusted Completion
Date:
March 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Linden Park, Brooklyn
Linden Boulevard, Miller Avenue, Stanley Avenue, Vermont Street
Community Board: 05
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024