Chester Playground Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct Chester Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2020
Projected Completion Date: October 2021
Completion Date: August 2022

Procurement

Start Date: August 2022
Projected Completion Date: May 2023
Adjusted Completion Date: March 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • City Council
  • Mayoral

Location

Chester Playground, Brooklyn
Chester Street between Sutter Avenue & Pitkin Avenue
Community Board: 16

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024