Chester Playground Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct Chester Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2020
Projected Completion Date:
October 2021
Completion Date:
August 2022
Procurement
Start Date: August 2022
Projected Completion Date:
May 2023
Adjusted Completion
Date:
March 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Chester Playground, Brooklyn
Chester Street between Sutter Avenue & Pitkin Avenue
Community Board: 16
Project Staff
Project Liaison: Davey Ives