This project will reconstruct the sitting area in Jacob Schiff Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2019
Projected Completion Date:
November 2020
Completion Date:
November 2020
Procurement
Start Date: November 2020
Projected Completion Date:
August 2021
Completion
Date:
May 2022
Construction
Start Date: June 2022
Projected Completion Date:
June 2023
Completion Date: June 2023
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Jacob H. Schiff Playground, Manhattan
Amsterdam Avenue between West 136th Street and West 138th Street
Community Board: 09
Project Staff
Project Liaison: Steve Simon