Gorman Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Gorman Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2019
Projected Completion Date:
October 2020
Completion Date:
December 2020
Procurement
Start Date: December 2020
Projected Completion Date:
August 2021
Completion
Date:
December 2022
Construction
Start Date: February 2023
Projected Completion Date:
February 2024
Completion Date: November 2023
Understand how we build parks.
Funding
Funding Source: City Council
Location
Gorman Playground, Queens
84th Street, 85th Street, 25th Avenue, 30th Avenue
Community Board: 03
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024