Gorman Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Gorman Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2019
Projected Completion Date: October 2020
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: August 2021
Completion Date: December 2022

Construction

Start Date: February 2023
Projected Completion Date: February 2024
Completion Date: November 2023

Understand how we build parks.

Funding

Total Funding: $3,032,000
Funding Source: City Council

Location

Gorman Playground, Queens
84th Street, 85th Street, 25th Avenue, 30th Avenue
Community Board: 03

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024