Dongan Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    86% complete

This project will reconstruct the play area and sidewalks at Dongan Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2020
Projected Completion Date: January 2021
Completion Date: May 2022

Procurement

Start Date: May 2022
Projected Completion Date: February 2023
Completion Date: December 2023

Construction

Start Date: March 2024
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $3,500,000
Funding Source: City Council

Location

Dongan Playground, Staten Island
Dongan Hills Avenue, Mason Avenue, Buel Avenue
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024