Dongan Playground Reconstruction
-
100% complete
-
100% complete
-
86% complete
This project will reconstruct the play area and sidewalks at Dongan Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2020
Projected Completion Date:
January 2021
Completion Date:
May 2022
Procurement
Start Date: May 2022
Projected Completion Date:
February 2023
Completion
Date:
December 2023
Construction
Start Date: March 2024
Projected Completion Date:
March 2025
Understand how we build parks.
Funding
Funding Source: City Council
Location
Dongan Playground, Staten Island
Dongan Hills Avenue, Mason Avenue, Buel Avenue
Community Board: 02
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024