Jacob Schiff Playground Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the synthetic turf field at Jacob Schiff Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: January 2021
Completion Date: December 2021

Construction

Start Date: February 2022
Projected Completion Date: February 2023
Completion Date: November 2022

Understand how we build parks.

Funding

Total Funding: $2,919,000
Funding Source: Mayoral

Location

Jacob H. Schiff Playground, Manhattan
Amsterdam Avenue Between West 136th Street and West 138th Street
Community Board: 09

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024