Jacob Schiff Playground Synthetic Turf Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the synthetic turf field at Jacob Schiff Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2019
Projected Completion Date:
May 2020
Completion Date:
April 2020
Procurement
Start Date: April 2020
Projected Completion Date:
January 2021
Completion
Date:
December 2021
Construction
Start Date: February 2022
Projected Completion Date:
February 2023
Completion Date: November 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Jacob H. Schiff Playground, Manhattan
Amsterdam Avenue Between West 136th Street and West 138th Street
Community Board: 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024