Linden Park Synthetic Turf Field and Rubberized Track Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the existing synthetic turf field and running track and construct new drinking fountains and sports field spray misters in Linden Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: August 2018
Completion Date: July 2018

Construction

Start Date: October 2018
Projected Completion Date: October 2019
Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $3,784,000
Funding Sources:
  • City Council
  • Mayoral

Location

Linden Park, Brooklyn
Linden Boulevard and Vermont Street
Community Board: 05

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024