Queens Roller Hockey Rinks Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct roller hockey rinks at Juniper Valley Park, Harvey Park, Mafera Park and College Point Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2015
Projected Completion Date:
October 2016
Completion Date:
December 2016
Procurement
Start Date: December 2016
Projected Completion Date:
September 2017
Completion
Date:
September 2017
Construction
Start Date: February 2018
Projected Completion Date:
February 2019
Completion Date: November 2018
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Locations
-
College Point Fields, Queens
130th Street & 23rd Avenue
Community Board: 07 -
Harvey Park, Queens
15 to 20 Avenues, East of Whitestone Expressway
Community Board: 07 -
Juniper Valley Park, Queens
Dry Harbor Road, 80th Street, Juniper Boulevard North, Juniper Boulevard South, Lutheran Avenue
Community Board: 05 -
Mafera Park, Queens
65 Place & Catalpa Avenue & 68 Avenue
Community Board: 05
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project