Queens Roller Hockey Rinks Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct roller hockey rinks at Juniper Valley Park, Harvey Park, Mafera Park and College Point Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2015
Projected Completion Date: October 2016
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: September 2017

Construction

Start Date: February 2018
Projected Completion Date: February 2019
Completion Date: November 2018

Understand how we build parks.

Funding

Total Funding: $1,747,000
Funding Sources:
  • City Council
  • Mayoral

Locations

  • College Point Fields, Queens
    130th Street & 23rd Avenue
    Community Board: 07
  • Harvey Park, Queens
    15 to 20 Avenues, East of Whitestone Expressway
    Community Board: 07
  • Juniper Valley Park, Queens
    Dry Harbor Road, 80th Street, Juniper Boulevard North, Juniper Boulevard South, Lutheran Avenue
    Community Board: 05
  • Mafera Park, Queens
    65 Place & Catalpa Avenue & 68 Avenue
    Community Board: 05
 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project