Jacob H. Schiff Playground Basketball and Handball Courts Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct basketball and handball courts at Jacob H. Schiff Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2017
Projected Completion Date:
June 2018
Completion Date:
May 2018
Procurement
Start Date: May 2018
Projected Completion Date:
February 2019
Completion
Date:
June 2019
Construction
Start Date: August 2019
Projected Completion Date:
August 2020
Completion Date: August 2020
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Jacob H. Schiff Playground, Manhattan
Amsterdam Avenue Between 136th Street and 138th Street
Community Board: 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024