Jacob H. Schiff Playground Basketball and Handball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct basketball and handball courts at Jacob H. Schiff Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: May 2018

Procurement

Start Date: May 2018
Projected Completion Date: February 2019
Completion Date: June 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2020
Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $942,000
Funding Sources:
  • City Council
  • Mayoral

Location

Jacob H. Schiff Playground, Manhattan
Amsterdam Avenue Between 136th Street and 138th Street
Community Board: 09

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024