Jacob Joffe Fields Adult Fitness Area Construction and Sport Courts Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the basketball and handball courts at Jacob Joffe Fields.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2015
Projected Completion Date:
September 2016
Completion Date:
December 2016
Procurement
Start Date: December 2016
Projected Completion Date:
September 2017
Completion
Date:
February 2018
Construction
Start Date: April 2018
Projected Completion Date:
April 2019
Completion Date: April 2019
Understand how we build parks.
Funding
Funding Source: City Council
Location
Jacob Joffe Fields, Brooklyn
Avenue K between 58th Street and 59th Street
Community Board: 18
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project