Citywide Energy Efficient Ballfield Lighting Retrofits (CNYG-2915M)
-
100% complete
-
100% complete
-
100% complete
This project will construct energy efficient ballfield lighting retrofits.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2014
Projected Completion Date:
February 2015
Completion Date:
March 2015
Procurement
Start Date: March 2015
Projected Completion Date:
December 2015
Completion
Date:
July 2016
Construction
Start Date: October 2016
Projected Completion Date:
October 2019
Completion Date: September 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Brigadier General Charles Young Playground, Manhattan
W. 145 St. to W. 143 St., Lenox Ave., and Harlem River
Community Board: 10 -
Castle Hill Little League Field, Bronx
Zerega Av bet Commerce Av & Gleason Av
Community Board: 09 -
City Line Park, Brooklyn
Atlantic & Fountain Avenues
Community Board: 05 -
De Witt Clinton Park, Manhattan
W. 52 St. To W. 54 St., 11 Ave. To 12 Ave.
Community Board: 04 -
Highland Park, Brooklyn
Interborough Pkwy, Jamaica Av, Bulver Pl
Community Board: 05, 05 -
Highland Park, Queens
Jamaica Avenue & Elton Street
Community Board: 05, 05 -
Linden Park, Brooklyn
Vermont St. bet. Linden Blvd. and Stanley Ave.
Community Board: 05 -
McCarren Park, Brooklyn
North 12th Street / Driggs Avenue / Lorimer Street / Bedford Avenue
Community Board: 01 -
Prospect Park, Brooklyn
Prospect Park West, Flatbush, Parkside, Ocean Avenues
Community Board: 06, 07, 08, 09, 14 -
St. John's Park, Brooklyn
Troy Avenue, Bergen Street, Prospect Place, Schenectady Avenue
Community Board: 08 -
Sternberg Park, Brooklyn
Montrose Avenue, Boerum, Lorimer, Leonard Streets
Community Board: 01
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025