Astoria Heights and Bowne Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom buildings at Astoria Heights Playground and Bowne Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2014
Projected Completion Date:
January 2016
Completion Date:
February 2016
Procurement
Start Date: February 2016
Projected Completion Date:
October 2016
Completion
Date:
December 2016
Construction
Start Date: February 2017
Projected Completion Date:
June 2018
Completion Date: July 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Astoria Heights Playground, Queens
30 Road between 45 Street and 46 Street
Community Board: 01 -
Bowne Playground, Queens
Union St. bet. Barclay Ave. and Sanford Ave.
Community Board: 07
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024