Astoria Heights and Bowne Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom buildings at Astoria Heights Playground and Bowne Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2014
Projected Completion Date: January 2016
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: October 2016
Completion Date: December 2016

Construction

Start Date: February 2017
Projected Completion Date: June 2018
Completion Date: July 2018

Understand how we build parks.

Funding

Total Funding: $4,470,000
Funding Source: Mayoral