Astoria Heights-JHS10 Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Astoria Heights Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2014
Projected Completion Date: November 2015
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: October 2016
Completion Date: September 2016

Construction

Start Date: November 2016
Projected Completion Date: May 2018
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $5,040,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Astoria Heights Playground, Queens
30th Road between 45th and 46th Streets
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025