Linden Park Adult Fitness Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct and adult fitness area and install fitness equipment at Linden Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2013
Projected Completion Date: December 2014
Completion Date: March 2015

Procurement

Start Date: March 2015
Projected Completion Date: December 2015
Completion Date: January 2016

Construction

Start Date: March 2016
Projected Completion Date: March 2017
Completion Date: October 2016

Understand how we build parks.

Funding

Total Funding: $280,000
Funding Sources:
  • City Council
  • Mayoral

Location

Linden Park, Brooklyn
Vermont Street and Stanley Avenue
Community Board: 05

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024