Linden Park Adult Fitness Area Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct and adult fitness area and install fitness equipment at Linden Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2013
Projected Completion Date:
December 2014
Completion Date:
March 2015
Procurement
Start Date: March 2015
Projected Completion Date:
December 2015
Completion
Date:
January 2016
Construction
Start Date: March 2016
Projected Completion Date:
March 2017
Completion Date: October 2016
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Linden Park, Brooklyn
Vermont Street and Stanley Avenue
Community Board: 05
Project Staff
Project Liaison: Davey Ives