Gateway Estates Phase 1 Playground and Public Restroom Building Construction - HVAC
-
100% complete
-
100% complete
-
100% complete
This project will construct the HVAC systems at the public restroom building at Gateway Estates.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2011
Projected Completion Date:
December 2014
Completion Date:
March 2015
Procurement
Start Date: March 2015
Projected Completion Date:
December 2015
Completion
Date:
June 2016
Construction
Start Date: September 2016
Projected Completion Date:
March 2019
Completion Date: February 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Berriman Playground, Brooklyn
Vandalia Avenue and Berriman Street, Erskine Street and Schroeders Avenue
Community Board: 05
Related Projects
Total Funding for These Related Projects:
Between $3 million and $10 million
Funding Source:
Mayoral
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024