Gateway Estates Phase 1 Playground and Public Restroom Building Construction - Electrical

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct electrical service to a playground and Public Restroom Building at Gateway Estates.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2011
Projected Completion Date: October 2013
Completion Date: April 2015

Procurement

Start Date: April 2015
Projected Completion Date: December 2015
Completion Date: March 2016

Construction

Start Date: September 2016
Projected Completion Date: March 2019
Completion Date: February 2019

Understand how we build parks.

Funding

Total Funding: $87,000
Funding Source: Mayoral

Location

Berriman Playground, Brooklyn
Vandalia Avenue and Berriman Street, Erskine Street and Schroeders Avenue
Community Board: 05

 

Related Projects

Total Funding for These Related Projects: Between $3 million and $10 million
Funding Source: Mayoral

Project Phase
Gateway Estates Phase 1 Playground and Public Restroom Building Construction Completed
Gateway Estates Phase 1 Playground and Public Restroom Building Construction - HVAC Completed
Gateway Estates Phase 1 Playground and Public Restroom Building Construction - Plumbing Completed