West Farms Park Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct West Farms Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2014
Projected Completion Date:
March 2015
Completion Date:
June 2016
Procurement
Start Date: June 2016
Projected Completion Date:
March 2017
Completion
Date:
January 2019
Construction
Start Date: April 2019
Projected Completion Date:
March 2020
Completion Date: April 2020
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Federal
- Mayoral
- State
Location
West Farms Rapids, Bronx
Along the western bank of the Bronx River between East Tremont Avenue and East 180th Street
Community Board: 06
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025