Paerdegat Athletic Center Air Conditioning Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the air conditioning equipment at Paerdegat Athletic Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2014
Projected Completion Date: January 2015
Completion Date: April 2015

Procurement

Start Date: April 2015
Projected Completion Date: January 2016
Completion Date: February 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: March 2020

Understand how we build parks.

Funding

Total Funding: $2,922,000
Funding Sources:
  • Federal
  • Mayoral

Location

Paerdegat Basin Park, Brooklyn
Paerdegat Avenue North between Paerdegat 13th Street and Seaview Avenue
Community Board: 18

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project