Paerdegat Athletic Center Air Conditioning Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the air conditioning equipment at Paerdegat Athletic Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2014
Projected Completion Date:
January 2015
Completion Date:
April 2015
Procurement
Start Date: April 2015
Projected Completion Date:
January 2016
Completion
Date:
February 2017
Construction
Start Date: March 2017
Projected Completion Date:
March 2018
Completion Date: March 2020
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Paerdegat Basin Park, Brooklyn
Paerdegat Avenue North between Paerdegat 13th Street and Seaview Avenue
Community Board: 18
Project Staff
Project Liaison: Davey Ives