Ferry Point Park West Public Restroom Building Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a public restroom building in the western section of Ferry Point Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2006
Projected Completion Date:
February 2014
Completion Date:
May 2014
Procurement
Start Date: May 2014
Projected Completion Date:
February 2015
Completion
Date:
August 2015
Construction
Start Date: February 2016
Projected Completion Date:
August 2017
Completion Date: March 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Ferry Point Park, Bronx
Bronx Whitestone Bridge, Schley Avenue, Westchester Creek and the East River
Community Board: 10
Related Projects
Total Funding for These Related Projects:
Between $3 million and $10 million
Funding Source:
Mayoral
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024