Ferry Point Park West Public Restroom Building Construction - Plumbing

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct the plumbing system in connection with the construction of a public restroom building in the western section of Ferry Point Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2006
Projected Completion Date: February 2014
Completion Date: May 2014

Procurement

Start Date: May 2014
Projected Completion Date: February 2015
Completion Date: July 2015

Construction

Start Date: July 2016
Projected Completion Date: December 2017
Completion Date: March 2018

Understand how we build parks.

Funding

Total Funding: $176,000
Funding Source: Mayoral

Location

Ferry Point Park, Bronx
Bronx Whitestone Bridge, Schley Avenue, Westchester Creek and the East River
Community Board: 10

 

Related Projects

Total Funding for These Related Projects: Between $3 million and $10 million
Funding Source: Mayoral

Project Phase
Ferry Point Park West Public Restroom Building Construction Completed
Ferry Point Park West Public Restroom Building Construction - Electrical Completed
Ferry Point Park West Public Restroom Building Construction - HVAC Completed

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024