Queens General Site Work (QG-1011M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct pavements, fencing, tennis courts, handball courts, and plantings in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2011
Completion Date: February 2012

Procurement

Start Date: February 2012
Projected Completion Date: November 2012
Completion Date: August 2012

Construction

Start Date: January 2013
Projected Completion Date: July 2014
Completion Date: July 2014

Understand how we build parks.

Funding

Total Funding: $1,504,000
Funding Sources:
  • Borough President
  • City Council
  • State

Locations

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024