Castle Hill Park Paths Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct paths and landscaping in Castle Hill Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2011
Projected Completion Date: June 2013
Completion Date: November 2013

Procurement

Start Date: November 2013
Projected Completion Date: August 2014
Completion Date: December 2014

Construction

Start Date: January 2015
Projected Completion Date: January 2016
Completion Date: January 2016

Understand how we build parks.

Funding

Total Funding: $434,000
Funding Source: Borough President

Location

Castle Hill Park, Bronx
Castle Hill Avenue and Hart Street
Community Board: 09

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024