Linden Park Handball Court and Bayview Playground Baseball Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project includes the reconstruction of Linden Park’s handball court and park entrance. The deteriorated asphalt will be replaced with new pavement to provide a safe and pleasant environment for park users. Additional features include a new planting area, expanded landscaping around park trees, the installation of new bike racks and accessible benches and the reconstruction of drainage systems for better water conservation.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2010
Completion Date:
February 2012
Procurement
Start Date: February 2012
Projected Completion Date:
October 2012
Completion
Date:
July 2013
Construction
Start Date: August 2013
Projected Completion Date:
August 2014
Completion Date: June 2014
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Locations
-
Bayview Playground, Brooklyn
S/S Seaview Avenue Opposite East 99 Street
Community Board: 18 -
Linden Park, Brooklyn
Linden Boulevard, Miller Avenue, Stanley Avenue, Vermont Street
Community Board: 05
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project