Estella Diggs Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct additional fencing, paths, seating and miscellaneous site amenities at Rocks & Roots Park (Estella Diggs).

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2012
Projected Completion Date: June 2014
Completion Date: October 2014

Procurement

Start Date: October 2014
Projected Completion Date: July 2015
Completion Date: July 2015

Construction

Start Date: October 2015
Projected Completion Date: October 2016
Completion Date: May 2017

Understand how we build parks.

Funding

Total Funding: $1,523,000
Funding Sources:
  • Borough President
  • City Council

Location

Estella Diggs Park, Bronx
East 167th Street between Third and Fulton Avenues
Community Board: 03

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024