Flatbush African Burial Ground

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct an African Burial Memorial Site at Bedford Avenue and Church Avenue.

Project Notes

Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.

Project Timeline

Design

Assigned & Start Date: April 2023
Projected Completion Date: October 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: City Council

Location

Flatbush African Burial Ground, Brooklyn
Bedford Avenue and Church Avenue
Community Board: 4

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024