Flatbush African Burial Ground

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct an African Burial Memorial Site at Bedford Avenue and Church Avenue.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2023
Projected Completion Date: October 2024
Adjusted Completion Date: December 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: City Council

Location

Flatbush African Burial Ground, Brooklyn
Bedford Avenue and Church Avenue
Community Board: 4

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/21/2025