Playground Eighty Nine Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Playground Eighty-Nine.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2013
Projected Completion Date:
November 2013
Completion Date:
July 2015
Procurement
Start Date: August 2015
Projected Completion Date:
January 2016
Completion
Date:
July 2015
Construction
Start Date: August 2015
Projected Completion Date:
January 2016
Completion Date: January 2016