Playground Eighty Nine Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Playground Eighty-Nine.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2013
Projected Completion Date: November 2013
Completion Date: July 2015

Procurement

Start Date: August 2015
Projected Completion Date: January 2016
Completion Date: July 2015

Construction

Start Date: August 2015
Projected Completion Date: January 2016
Completion Date: January 2016

Understand how we build parks.

Funding

Total Funding: $1,000,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Playground Eighty Nine LXXXIX, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024