Paerdegat Basin Park Yacht Clubs Reconstruction (Hurricane Sandy)
-
5% complete
-
0% complete
-
0% complete
This project will reconstruct Paerdegat Squadron, Midget Squadron, Diamond Point, and Hudson River Yacht Clubs in Paerdegat Basin Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2022
Projected Completion Date:
April 2024
Adjusted Completion Date:
April 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Paerdegat Basin Park, Brooklyn
Bergen Avenue, East 76th Street, Paerdegat Avenue North
Community Board: 18
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024