Staten Island Tree-Damaged Sidewalk Reconstruction FY21

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct sidewalks damaged by trees in Staten Island.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2021
Projected Completion Date: September 2021
Completion Date: April 2021

Procurement

Start Date: April 2021
Projected Completion Date: January 2022
Completion Date: November 2021

Construction

Start Date: July 2021
Projected Completion Date: July 2023
Completion Date: March 2023

Understand how we build parks.

Funding

Total Funding: $2,821,000
Funding Source: Mayoral

Location

Various locations in Staten Island

Project Staff

Contact NYC Parks about this project