Manhattan East Side Coastal Resiliency Stormwater Greenstreets Construction
-
5% complete
-
0% complete
-
0% complete
This project will construct greenstreets to capture stormwater in Community Boards 3 and 6 in Manhattan.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2021
Projected Completion Date:
September 2023
Adjusted Completion Date:
February 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 11/22/2024