Manhattan East Side Coastal Resiliency Stormwater Greenstreets Construction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct greenstreets to capture stormwater in Community Boards 3 and 6 in Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2021
Projected Completion Date: September 2023
Adjusted Completion Date: February 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Various locations in Manhattan

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024