Fort Greene Park Entrances, Paths, Plaza and Drainage Infrastructure Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the entrances, paths, plaza and drainage infrastructure at Fort Greene Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2021
Projected Completion Date: December 2021
Completion Date: September 2023

Procurement

Start Date: September 2023
Projected Completion Date: September 2024
Adjusted Completion Date: March 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Fort Greene Park, Brooklyn
Myrtle Ave., DeKalb Ave. between Washington Park and St. Edward's St.
Community Board: 02

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024