Bronx Street Tree Planting FY21
-
100% complete
-
100% complete
-
100% complete
This project will plant new and replacement trees in street tree beds that have been previously excavated and backfilled with soil and compost in the Bronx.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2021
Projected Completion Date:
April 2021
Completion Date:
February 2021
Procurement
Start Date: February 2021
Projected Completion Date:
November 2021
Completion
Date:
July 2021
Construction
Start Date: September 2021
Projected Completion Date:
January 2022
Completion Date: October 2021
Understand how we build parks.
Funding
Funding Source: Private