Pelham Bay Park Forest Tree Replacement

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will plant replacement trees and restore native species habitat within forested natural areas in Pelham Bay Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2021
Projected Completion Date: January 2022
Completion Date: December 2021

Procurement

Start Date: December 2021
Projected Completion Date: September 2022
Completion Date: March 2024

Construction

Start Date: September 2024
Projected Completion Date: September 2027

Understand how we build parks.

Funding

Total Funding: $3,244,000
Funding Source: Mayoral

Location

Pelham Bay Park, Bronx
South of City Island Circle between Rodmans Neck Road and City Island Road
Community Board: 10, 12

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024