Pelham Bay Park Forest Tree Replacement

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will plant replacement trees and restore native species habitat within forested natural areas in Pelham Bay Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2021
Projected Completion Date: January 2022
Completion Date: December 2021

Procurement

Start Date: December 2021
Projected Completion Date: September 2022
Completion Date: March 2024

Construction

Start Date: September 2024
Projected Completion Date: September 2027

Understand how we build parks.

Funding

Total Funding: $3,244,000
Funding Source: Mayoral

Location

Pelham Bay Park, Bronx
South of City Island Circle between Rodmans Neck Road and City Island Road
Community Board: 10, 12

 

Project Staff

Contact NYC Parks about this project

Last updated: 03/28/2025