Coney Island Lifeguard Station Electrical Service Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct electrical service to the lifeguard station at Coney Island Boardwalk.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2020
Projected Completion Date: February 2021
Completion Date: February 2021

Procurement

Start Date: February 2021
Projected Completion Date: October 2021
Completion Date: May 2021

Construction

Start Date: June 2021
Projected Completion Date: June 2022
Completion Date: June 2021

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Coney Island Beach & Boardwalk, Brooklyn
Coney Island Boardwalk near Coney Island Avenue
Community Board: 13, 15

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024