Fort Totten Park Commander's House Porches Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    14% complete

This project will reconstruct the porches at the Commander's House in Fort Totten Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2021
Projected Completion Date: January 2022
Completion Date: March 2022

Procurement

Start Date: March 2022
Projected Completion Date: December 2022
Completion Date: April 2024

Construction

Start Date: May 2024
Projected Completion Date: November 2025

Understand how we build parks.

Funding

Total Funding: $954,000
Funding Source: Mayoral

Location

Fort Totten Park, Queens
422A Weaver Avenue
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024