William McCray Playground Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct William McCray Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2022
Projected Completion Date:
January 2023
Completion Date:
January 2023
Procurement
Start Date: January 2023
Projected Completion Date:
October 2023
Completion
Date:
September 2024
Construction
Start Date: September 2024
Projected Completion Date:
September 2025
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
William McCray Playground, Manhattan
West 138th Street between 5th Avenue and Malcolm X Boulevard
Community Board: 10
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024