Penn South Playground Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct Penn South Playground.

Project Notes

Project Update: The project has entered procurement and is being reviewed and prepared for solicitation.

Project Timeline

Design

Assigned & Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: June 2024

Procurement

Start Date: June 2024
Projected Completion Date: March 2026

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Penn South Playground, Manhattan
West 26th Street between 8th and 9th Avenues
Community Board: 04

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 03/28/2025