Bleecker Playground Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct Bleecker Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2022
Projected Completion Date:
May 2023
Completion Date:
May 2023
Procurement
Start Date: May 2023
Projected Completion Date:
May 2024
Adjusted Completion
Date:
February 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Bleecker Playground, Manhattan
Bleecker, Hudson, and West 11th Streets
Community Board: 02
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024