Brooklyn Tree Planting and Greenstreets Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will plant street trees and construct Greenstreets on Union Street.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2015
Projected Completion Date: February 2022
Completion Date: June 2022

Procurement

Start Date: June 2022
Projected Completion Date: March 2023
Adjusted Completion Date: September 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • City Council
  • Mayoral

Location

Union Street between Bond Street and 3rd Avenue

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024