East 66th Street Greenstreets Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct two Greenstreets on East 66th Street with new plantings.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2015
Projected Completion Date: September 2022
Completion Date: March 2022

Procurement

Start Date: March 2022
Projected Completion Date: December 2022
Completion Date: March 2024

Construction

Start Date: March 2024
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $90,000
Funding Source: Mayoral

Location

East 66th Street between 2nd Avenue and 3rd Avenue

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024