Queens Medians Planting and Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct and replant Bell Malls, Merrick Boulevard Mall and Elmjack Mall.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2015
Projected Completion Date: February 2022
Completion Date: July 2022

Procurement

Start Date: July 2022
Projected Completion Date: April 2023
Completion Date: July 2024

Construction

Start Date: August 2024
Projected Completion Date: February 2026

Understand how we build parks.

Funding

Total Funding: $1,616,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

  • Bell Malls, Queens
    Bell Boulevard, 48 Avenue to Horace Harding Expressway
    Community Board: 11
  • Elmjack Mall, Queens
    75th Street, 37th Avenue and Roosevelt Avenue
    Community Board: 03, 04
  • DOT (Non-Parks) Property in Queens
 

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024