Crotona Park Bathhouse Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    83% complete

This project will reconstruct a portion of the roof at Crotona Park Bathhouse.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2021
Projected Completion Date: February 2022
Completion Date: March 2022

Procurement

Start Date: March 2022
Projected Completion Date: December 2022
Completion Date: October 2023

Construction

Start Date: February 2024
Projected Completion Date: December 2025

Understand how we build parks.

Funding

Total Funding: $3,236,000
Funding Source: Mayoral

Location

Crotona Park, Bronx
1700 Fulton Avenue
Community Board: 03

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024