Crotona Park Bathhouse Roof Reconstruction
-
100% complete
-
100% complete
-
84% complete
This project will reconstruct a portion of the roof at Crotona Park Bathhouse.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2021
Projected Completion Date:
February 2022
Completion Date:
March 2022
Procurement
Start Date: March 2022
Projected Completion Date:
December 2022
Completion
Date:
October 2023
Construction
Start Date: February 2024
Projected Completion Date:
December 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Crotona Park, Bronx
1700 Fulton Avenue
Community Board: 03
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025