Randall's Island Park Citywide Services Complex Fleet Shop Exhaust System Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the exhaust system for the Fleet Shop within the Citywide Services Complex and Garage at Randall's Island Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2021
Projected Completion Date: April 2021
Completion Date: April 2021

Procurement

Start Date: April 2021
Projected Completion Date: January 2022
Completion Date: December 2022

Construction

Start Date: May 2023
Projected Completion Date: February 2024
Completion Date: October 2023

Understand how we build parks.

Funding

Total Funding: $488,000
Funding Source: Mayoral

Location

Randall's Island Park, Manhattan
20 Bronx Shore Road
Community Board: 11

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project