Randall's Island Park Citywide Services Complex Fleet Shop Exhaust System Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the exhaust system for the Fleet Shop within the Citywide Services Complex and Garage at Randall's Island Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2021
Projected Completion Date:
April 2021
Completion Date:
April 2021
Procurement
Start Date: April 2021
Projected Completion Date:
January 2022
Completion
Date:
December 2022
Construction
Start Date: May 2023
Projected Completion Date:
February 2024
Completion Date: October 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Randall's Island Park, Manhattan
20 Bronx Shore Road
Community Board: 11
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project