Udall's Park Preserve Forest Restoration
-
100% complete
-
0% complete
-
0% complete
This project will restore native species habitat within forested natural areas in Udall's Park Preserve.
Project Notes
Project Update: Design is complete and permitting and legal review of the contract are in progress.
Project Timeline
Design
Assigned & Start Date: January 2021
Projected Completion Date:
January 2022
Completion Date:
January 2022
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Udall's Park Preserve, Queens
40th Avenue between Douglas Road and Little Neck Parkway
Community Board: 11
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024