Sol Bloom Playground Basketball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball court in Sol Bloom Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2021
Projected Completion Date: January 2022
Completion Date: January 2022

Procurement

Start Date: January 2022
Projected Completion Date: October 2022
Completion Date: July 2023

Construction

Start Date: September 2023
Projected Completion Date: September 2024
Completion Date: August 2024

Understand how we build parks.

Funding

Total Funding: $600,000
Funding Source: City Council

Location

Sol Bloom Playground, Manhattan
West 91st Street and West 92nd Street between Columbus Avenue and Central Park West
Community Board: 07

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project