Design
Assigned & Start Date: January 2021
Projected Completion Date:
January 2022
Completion Date:
January 2022
Procurement
Start Date: January 2022
Projected Completion Date:
October 2022
Completion
Date:
July 2023
Construction
Start Date: September 2023
Projected Completion Date:
September 2024
Completion Date: August 2024
Understand how we build parks.
Funding
Funding Source: City Council
Location
Sol Bloom Playground, Manhattan
West 91st Street and West 92nd Street between Columbus Avenue and Central Park West
Community Board: 07
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025