Alexander Hamilton Playground Basketball Court Reconstruction
-
100% complete
-
100% complete
-
14% complete
This project will reconstruct the basketball court at Alexander Hamilton Playground.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2021
Projected Completion Date:
February 2022
Completion Date:
February 2023
Procurement
Start Date: February 2023
Projected Completion Date:
October 2023
Completion
Date:
June 2024
Construction
Start Date: September 2024
Projected Completion Date:
September 2025
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Alexander Hamilton Playground, Manhattan
Hamilton Place between West 140th Street and West 141st Street
Community Board: 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025