Alexander Hamilton Playground Basketball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    14% complete

This project will reconstruct the basketball court at Alexander Hamilton Playground.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2021
Projected Completion Date: February 2022
Completion Date: February 2023

Procurement

Start Date: February 2023
Projected Completion Date: October 2023
Completion Date: June 2024

Construction

Start Date: September 2024
Projected Completion Date: September 2025

Understand how we build parks.

Funding

Total Funding: $1,355,000
Funding Sources:
  • Borough President
  • City Council

Location

Alexander Hamilton Playground, Manhattan
Hamilton Place between West 140th Street and West 141st Street
Community Board: 09

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025