Hamilton Fish Park Playground Reconstruction
-
100% complete
-
85% complete
-
0% complete
This project will reconstruct the playground at Hamilton Fish Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2021
Projected Completion Date:
June 2022
Completion Date:
November 2022
Procurement
Start Date: November 2022
Projected Completion Date:
August 2023
Adjusted Completion
Date:
December 2024
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Hamilton Fish Park, Manhattan
East Houston Street between Sheriff Street and Pitt Street
Community Board: 03
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024