Jamaica Playground Multipurpose Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the multipurpose play area in Jamaica Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2021
Projected Completion Date: June 2022
Completion Date: June 2022

Procurement

Start Date: June 2022
Projected Completion Date: March 2023
Completion Date: September 2024

Construction

Start Date: September 2024
Projected Completion Date: September 2024

Understand how we build parks.

Funding

Total Funding: $4,800,000
Funding Source: City Council

Location

Jamaica Playground, Queens
160th Street between 109th Avenue and Brinkerhoff Avenue
Community Board: 12

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024