Jamaica Playground Multipurpose Play Area Reconstruction
-
100% complete
-
100% complete
-
16% complete
This project will reconstruct the multipurpose play area in Jamaica Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2021
Projected Completion Date:
June 2022
Completion Date:
June 2022
Procurement
Start Date: June 2022
Projected Completion Date:
March 2023
Completion
Date:
September 2024
Construction
Start Date: September 2024
Projected Completion Date:
September 2025
Understand how we build parks.
Funding
Funding Source: City Council
Location
Jamaica Playground, Queens
160th Street between 109th Avenue and Brinkerhoff Avenue
Community Board: 12
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024