Captain Mario Fajardo Park Playground and Sports Courts Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the playground, basketball courts, and handball courts in Captain Mario Fajardo Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2021
Projected Completion Date:
February 2022
Completion Date:
August 2022
Procurement
Start Date: August 2022
Projected Completion Date:
May 2023
Adjusted Completion
Date:
March 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Kissena Corridor Park, Queens
Kissena Boulevard and Booth Memorial Avenue
Community Board: 07
Project Staff
Project Liaison: Meira Berkower