Cambria Playground Reconstruction
-
90% complete
-
0% complete
-
0% complete
This project will reconstruct Cambria Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2021
Projected Completion Date:
April 2022
Adjusted Completion Date:
November 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Cambria Playground, Queens
121st Avenue and Francis Lewis Boulevard near 222nd Street
Community Board: 13
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024